Mapleton City Culinary and Secondary Waterlines

The project involved replacement of undersized and aging City waterlines with 4,500 feet of 8-inch ductile iron pipe and 2,700 feet of 12-inch ductile iron pipe. The work included new valves, connections to existing pipes, and replacement of service lines and meters. Also included in the contract was more than 15,500 feet of 8-inch and 12-inch C-900 PVC pipe that was added to the secondary water system.

Location: Mapleton, Utah